New apartment handover at The Ellinikon: a checklist for overseas owners.
Handover is not one ceremonial appointment. It is a controlled sequence of legal, technical and practical steps. This checklist helps an owner abroad prepare the right people, evidence and follow-up.

The Ellinikon is moving through a long residential delivery cycle rather than one completion date. The official residential pages currently publish project-specific estimates across Riviera residences and Little Athens, with many Little Athens phase-one projects scheduled around 2027–2028 and Riviera Tower listed for completion in the first half of 2027. Those are development estimates, not a substitute for the notices and contractual timetable attached to your own purchase.
For an overseas owner, the challenge is less about distance on the handover day than control across the weeks before and after it. A key may be delivered while a defect remains open. A smart-home account may exist without being transferred. A photographed scratch may have no reference number. A contractor may say work is complete while nobody acting for the owner has revisited the unit. This guide turns those loose moments into one process.
First: define what “handover” means in your documents
People use “handover,” “delivery,” “completion,” “acceptance” and “possession” interchangeably. Your contract may not. Before arranging flights or representatives, ask your Greek lawyer to explain the exact event being scheduled, the notice procedure, any prerequisites, the effect of signing, the treatment of incomplete items, warranty or defect mechanisms, and whether funds or documents remain outstanding.
Do not rely on a generic online checklist for legal deadlines. Estia can help organize information and attend within written authority, but we do not advise whether a legal notice is valid or whether you should accept delivery. That decision belongs with you and your lawyer, informed by your engineer's findings.
Build the handover team before the appointment
Greek lawyer
Reviews contractual status, authority, notices, signing requirements and legal remedies. Confirms what your representative may sign, if anything.
Licensed engineer
Performs technical inspection or snagging, interprets plans and specifications, and provides professional findings within their discipline.
Owner or attorney
Makes acceptance, cost and priority decisions. A power of attorney must match the intended acts and should be prepared by the lawyer.
Local owner-side representative
Coordinates access, records practical delivery, photographs condition, manages an action log and supports follow-up after the technical visit.
One person may be present alongside another, but the roles remain distinct. A property-care provider should not sign legal acceptance unless properly authorized and advised, and should not issue a technical certificate without the required professional capacity. Clear boundaries make the evidence stronger, not weaker.
Two to four weeks before handover
Confirm the appointment and access
- Obtain the date, time, meeting point, named contact and expected duration in writing.
- Confirm who may attend and whether identification, advance registration or contractor insurance is required.
- Ask whether electricity, water, hot water, cooling, smart-home functions and private amenities will be operational for testing.
- Clarify whether the engineer will have enough time and access to perform the agreed inspection.
- If you cannot attend, ensure the developer and building security have the correct representative details before the day.
Create one source-of-truth folder
Store the executed purchase documents, approved plans and specifications, variation schedule, finish selections, appliance list, correspondence on agreed changes, payment confirmations, handover notice, engineer instructions and identity documents in a controlled folder. Avoid using a long email chain as the only record. Give each adviser only the information needed for their role.
Prepare the inspection structure
Your engineer will use a professional method appropriate to the property. Separately, the owner-side record should identify spaces consistently: entrance, living area, kitchen, bedroom one, bedroom two, bathrooms, plant cupboards, terraces, storage, parking and every exclusive-use area. Use the same labels in photographs and the action log. A statement such as “mark on wall” is weak; “bedroom two, north wall beside balcony door, item H-017” can be found again.
Documents and items to request at handover
The exact package varies by project and contract, so ask the responsible party for a written index. Depending on the residence, the practical delivery pack may include:
- All apartment, storage, parking, mailbox and private-gate keys, with quantities recorded.
- Access cards, remotes, fobs and instructions for replacement or deactivation.
- Alarm, intercom and smart-home setup or transfer instructions, without placing passwords in an insecure report.
- Appliance, HVAC, water-heating and specialist equipment manuals.
- Warranty contacts, service intervals and the process for reporting a defect.
- Meter identifiers and readings for private electricity, water or other utilities where applicable.
- Parking and storage identification, boundaries and access procedure.
- Building regulations, resident contact route, emergency procedures and moving or contractor rules.
- Information on service charges, reserves, billing frequency and the appointed building manager.
- Approved final selections or variation records needed to compare what was delivered.
Your lawyer and engineer should determine which formal certificates and legal or technical documents must also be delivered. The list above is operational; it is not a complete legal completion schedule.
What to record during the walkthrough
Arrival evidence
Start with the date, attendees and the condition in which the residence was first accessed. Photograph each room from a repeatable wide angle before focusing on details. Record whether protective materials, tools or contractor belongings remain. If utilities are not active, state that plainly instead of marking untested systems as satisfactory.
Openings, security and finishes
Doors and windows should be operated where permitted, with attention to closing, locking, seals, handles and visible frame damage. Shutters, screens and balcony doors should be included where fitted. Observe floors, walls, ceilings, joinery, stone, tiles and sanitary finishes under normal viewing conditions. The engineer decides whether an item is technically defective; the owner-side record preserves what was visible and where.
Accessible plumbing points
Where water is active and the engineer's process allows it, accessible taps, mixers, basins, showers, baths, WCs, visible connections and drainage behavior can be observed. Photograph meter readings and any visible moisture. Do not state that plumbing is “fully tested” if concealed pipework or uncommissioned systems were outside the check.
Electrical, cooling and smart-home functions
Record whether power was available and which accessible lights, controls, outlets or supplied appliances were checked. Cooling, heating, ventilation, underfloor systems, blinds and smart-home functions may require commissioning or specialist access. Keep credentials out of general photo reports. A failed connection may be an account-transfer issue rather than a hardware defect, so record the observed behavior before assigning cause.
Terraces and exclusive-use areas
Large balconies, roof gardens, private gardens and pools create obligations beyond the apartment interior. Record visible surfaces, drainage points, railings, doors, irrigation, planting condition and supplied equipment within the authorized scope. A professional should assess waterproofing, pool systems, structural elements and safety compliance. Establish which features are shared, private or exclusive-use because that classification affects future maintenance.
Storage and parking
Confirm that the designated areas can be located and accessed with the delivered keys or credentials. Photograph identifiers and the initial visible condition. Check practical dimensions or installations only where your engineer or contract requires it; do not infer legal boundaries from a painted line or verbal statement.
How to build a useful defect and action log
A folder of photographs is not a management system. Each item should have a unique number, location, short factual description, photograph, date recorded, responsible contact, priority, agreed next step, target date if one has been formally given, and final evidence. Keep technical findings linked to the engineer's report rather than rewriting them in less precise language.
| Field | Good record | Avoid |
|---|---|---|
| Location | Kitchen, tall cabinet beside refrigerator. | Kitchen problem. |
| Observation | Upper hinge makes contact; door does not close flush. | Bad cabinet. |
| Evidence | Wide view plus close image, item H-023. | One cropped image with no context. |
| Status | Reported 19 Oct; access requested; revisit pending. | They said they will fix it. |
| Closure | Revisited, operated normally, after-photo attached. | Marked complete from an email only. |
Priority also needs discipline. An active leak or unsecured opening is not equal to a cosmetic paint mark. Your engineer and lawyer should advise where a finding affects safety, use, contractual rights or formal notice. The local coordinator can then route access and evidence according to that priority.
The first 72 hours after handover
- Back up the evidence. Store the dated report, engineer's documents, keys register, meter photographs and delivery index in at least two secure places.
- Issue formal notices correctly. Your lawyer should confirm who must receive what, in which form and by which deadline. A WhatsApp message may be useful operationally but may not satisfy a contractual notice process.
- Secure access. Confirm custody of every key, fob, code and alarm credential. Deactivate anything unaccounted for through the approved building procedure.
- Activate private services. Utilities, internet, insurance and specialist maintenance should be arranged in the owner's name or authorized structure as advised.
- Schedule the first follow-up. Open items need a real revisit. Agree who will attend and what evidence counts as closure.
The first 30 days: watch how the home behaves
Some issues become visible only after occupation, rain, regular water use or a period of closed-up conditions. A post-handover routine can observe accessible areas for moisture, drainage behavior, cooling performance, door and shutter operation, smart-home connectivity and private amenity servicing. Again, observation is not diagnosis. A pattern is documented and escalated to the relevant specialist.
Furniture deliveries and fit-out work can also create new damage after the developer's handover. Photograph the residence before movers enter, follow the building's delivery rules, protect common and private surfaces, and record the final condition. Keep original handover items separate from later contractor or furnishing items so responsibility does not become blurred.
What Estia can and cannot do
Subject to access, written authorization and scheduling, Estia can coordinate attendance, create an owner-side photographic baseline, register keys and access items, record utility readings, maintain a practical action log, arrange approved supplier access and revisit completed items. We can then transition the residence into regular documented home checks, maintenance coordination or arrival preparation.
Estia does not replace your lawyer or licensed engineer, certify building work, interpret contractual acceptance, guarantee defect remedies or approve unbounded expenditure. We also do not claim that a visual report proves the condition of concealed elements. Our role is owner-side operational visibility and follow-through.
Your final pre-handover checklist
- Lawyer has explained the event, authority and notice deadlines.
- Licensed engineer is appointed and has the necessary documents and access.
- Representative authority is written and accepted by the relevant parties.
- Space names and evidence numbering are agreed before photographs begin.
- Keys, fobs, remotes, meters, manuals and credentials have an inventory.
- Untested systems will be labelled untested, not assumed satisfactory.
- Every action has an owner, status and closure requirement.
- Building-management contacts, rules and service-charge route are recorded.
- Private amenities have separate maintenance and access plans.
- The first follow-up visit is scheduled before the handover file goes quiet.
If you still need to define the distinction between common and private responsibility, read what The Ellinikon building manager covers and what the owner still needs. For ongoing support, see Estia's Ellinikon property management service for owners abroad.
Tell us the project, expected timing, where you live and which advisers are already appointed. We will identify what Estia can coordinate and what must remain with your lawyer or engineer. Request a discovery call.
Primary sources and further reading
- The Ellinikon — current residential projects and published completion estimates
- The Ellinikon — residential manager, service charges and private-area responsibilities
- The Ellinikon — Riviera Tower construction progress and current stated completion
- The Ellinikon — Riviera residence and amenity overview
Editorial note: Estia Greek Home is independent and is not affiliated with The Ellinikon or Lamda Development. This checklist is general operational information, not legal, engineering, insurance, investment or contractual advice.